Verifying workload submission
Now verify that Tivoli Workload Scheduler for z/OS can submit work and that the work is sent to the correct destination.
Controlling system
You can use this procedure for the controlling system:
- Create a workstation description, leave the destination field blank. This means that operations will be submitted to the system where the controller is started.
- Create an application description. Define at least one operation
on the workstation you have created. Submit a daily planning extend
or replan batch job to include the new workstation in the current
plan.
Add an occurrence of this application to the current plan.
- Verify that the operations run successfully on this system and that they are reported as complete in the current plan.
- Check that submit events are created in the event data set for the controlling system (see Verifying job submission).
Controlled systems
If you have controlled Tivoli Workload Scheduler for z/OS systems in your configuration, you can use this procedure to check that work is sent to these destinations, that it is submitted, and that events are returned to the controller:
- Create a workstation description for each destination. In the destination field, remember to specify the submit/release data set name, the XCF member name of the tracker, the tracker VTAM® application ID, or the tracker TCP/IP destination name, depending on the connection. Ensure that the trackers are active.
- Add an application occurrence to the current plan with operations defined on each of the workstations.
- Verify that the operations run successfully on the correct system and that they are reported as complete in the current plan.
- Check that submit events are created in the event data set for each controlled system (see Verifying job submission).
If your configuration includes a MAS complex, you can specify only one workstation description to represent all systems in the complex. If this is the case, ensure that a job is run on each system in the complex. Verify that events are received at the controller by checking that the operations are reported as complete in the current plan.
- If you create a workstation description after the current plan has been created, you must either replan or extend the current plan to use this workstation.
- You must also specify workstation destinations in the ROUTOPTS initialization statement. You must restart the controller if you update ROUTOPTS.