Setting a custom baseline for project groupings

You can set a custom baseline for specified project groupings.

About this task

ccm pg|project_grouping -scb|-set_custom_baseline baseline_spec project_grouping_spec...
baseline_spec...
Specifies the baseline to be used by the project grouping. See Baseline specification for more information.
project_grouping_spec
Specifies which project groupings to set the custom baseline for. See Project grouping specification for details.