CPO3994I   No more defined capacity is needed for LPAR LPAR name of CPC CPC name with system system name in sysplex sysplex name

Explanation

The Provisioning Manager is in analysis mode and detected that, according to the policy and the current workload situation, no additional defined capacity is needed for the referenced LPAR/system. Currently the Provisioning Manager doesn't manage any defined capacity for the referenced LPAR/system.

User response

Check whether the situation is correctly identified. If the situation is not correctly identified, then adjust the policy.