Start of change

CPO1066I   Activation level change to number SAPs successfully initiated for CPC name

Explanation

The ACTIVATE RESOURCE command with the CPC and SAP parameters set to the referenced CPC name and amount of SAP processors has been issued. The command processing successfully initiated activation of the new number of temporary SAP processors. The activation may take some time to complete.

User response

None.

End of change