z/OS Planning for Installation
Previous topic | Next topic | Contents | Contact z/OS | Library | PDF


Step 6. Customize and test the target system

z/OS Planning for Installation
GA32-0890-02

  1. If upgrading, perform the post-first-IPL migration tasks for z/OS®. These migration actions were identified in Step 1 and have a timing of "after the first IPL of z/OS V2R1" in z/OS Migration.

    Reference information: z/OS publications (http://www.ibm.com/eserver/zseries/zos/bkserv/)

  2. If upgrading, perform the post-first-IPL migration tasks for IBM® middleware, IBM applications, and ISV products. These migration actions were identified in Step 1.

    Reference information: IBM product publications and ISV publications.

  3. If installing for the first time, perform the customization tasks that you identified in Step 1.

    Reference information: z/OS publications (http://www.ibm.com/eserver/zseries/zos/bkserv/), IBM product publications, and ISV publications.

  4. IPL the customized system. Follow local procedures.
  5. Test the customized system. Use the test cases that you identified in Step 1.

Go to the previous page Go to the next page




Copyright IBM Corporation 1990, 2014