Error description

  • The "When will Tasks go Overdue" chart in the My Team
    Performance dashboard does not always work properly.  In
    specific time zones, and/or with Daylight Savings Time enabled,
    the chart may not display the correct set of tasks that will go
    overdue, because of incorrect calculation of the difference
    between the due time and the current time for tasks.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:  Users of BPM Express, BPM Standard, and     *
    *                  BPM Advanced.                               *
    ****************************************************************
    * PROBLEM DESCRIPTION: The "When will Tasks go Overdue"        *
    *                      chart in the My Team Performance        *
    *                      dashboard does not always work          *
    *                      properly.  In specific time zones,      *
    *                      and/or with Daylight Savings Time       *
    *                      enabled, the chart may not display      *
    *                      the correct set of tasks that will go   *
    *                      overdue, because of incorrect           *
    *                      calculation of the difference between   *
    *                      the due time and the current time for   *
    *                      tasks.                                  *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    The bar graph on the "When will Tasks go Overdue" chart, and
    the task list table that is populated when clicking on a bar
    on the graph, retrieve timestamp values from the database
    representing the "due times" for tasks.  Those times are
    stored in the database based on the server's time zone.  While
    the task list table displayed due dates based on the server
    time zone, the graph displayed due dates based on the
    browser time zone.  As a result, clicking on a bar (date) in
    the graph could fail to display the correct set of tasks for
    the date corresponding to the clicked bar, if the due time
    fell on different dates for the two time zones.  Daylight
    Savings Time offsets could also influence this behavior.
    

Problem conclusion

  • Changing the bar graph to render based on the server time zone
    (for consistency with the database and the task list table)
    resolves the issue.
    
    An interim fix for Business Process Manager Version 8.0.1.0 has
    been published to Fix Central.  Please refer to the separate
    file that is automatically downloaded with the interim fix
    for prerequisite information and installation/uninstallation
    instructions.  Note that this interim fix also contains the fix
    for APAR JR45100
    (http://www.ibm.com/support/docview.wss?uid=swg1JR45100);
    there is not a separate interim fix for that APAR.
    

Temporary fix

Comments

APAR Information

  • APAR number

    JR45101

  • Reported component name

    BPM STANDARD

  • Reported component ID

    5725C9500

  • Reported release

    801

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2012-12-11

  • Closed date

    2013-03-29

  • Last modified date

    2013-03-29

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    BPM STANDARD

  • Fixed component ID

    5725C9500

Applicable component levels

  • R800 PSY

       UP

[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSFTDH","label":"IBM Business Process Manager Standard"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"8.0.1","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
11 October 2021