Section 8. Recovery plan for hot site

An alternate hot site plan should provide for an alternative (backup) site. The alternate site has a backup system for temporary use while the home site is being reestablished.

  1. Notify ____________ of the nature of the disaster and of its desire for a hot site.
  2. Request air shipment of modems to ____________ for communications. (See ____________ for communications for the hot site.)
  3. Confirm in writing the telephone notification to ____________ within 48 hours of the telephone notification.
  4. Begin making necessary travel arrangements to the site for the operations team.
  5. Confirm that you have enough save media and that it is packed for shipment to restore on the backup system.
  6. Prepare a purchase order to cover the use of the backup system.
  7. Review the checklist for all necessary materials before departing to the hot site.
  8. Make sure that the disaster recovery team at the disaster site has the necessary information to begin restoring the site.
  9. Provide for travel expenses (cash advance).
  10. After arriving at the hot site, contact home base to establish communications procedures.
  11. Review materials brought to the hot site for completeness.
  12. Start to load the system from the save media.
  13. Begin normal operations as soon as possible:
    1. Daily jobs
    2. Daily saves
    3. Weekly saves
  14. Plan the schedule to back up the hot-site system in order to restore on the home-base computer.