z/OS Communications Server: SNA Diagnosis Vol 1, Techniques and Procedures
Previous topic | Next topic | Contents | Contact z/OS | Library | PDF


LU-LU session established using ISR routing

z/OS Communications Server: SNA Diagnosis Vol 1, Techniques and Procedures
GC27-3667-00

Problem statement
The LU-LU session activates, but no RTP connections are established.
Common symptoms
No message IST1488I was received before LU-LU session activation.
Probable cause
VTAM® determined that the session path is not HPR capable:
  • One or more connections between nodes in the session path are not HPR capable.
  • The session path does not terminate with an HPR tower node. (If the terminating node is VTAM, it must specify the start option HPR=RTP or take the default).
User response
Reconfigure the session path to include HPR capable links and terminate with an HPR tower node.

Go to the previous page Go to the next page




Copyright IBM Corporation 1990, 2014