- Perform as many z/OS® migration
actions as possible on the existing (old) system. These are the
preinstallation migration actions that you identified in Step 1, which
have a timing of "before installing z/OS V2R1" in z/OS Migration.
These migration actions include installing the coexistence and fallback
PTFs that you identified in Step 1 and ordered in Step 2.
Reference
information: z/OS publications
(http://www.ibm.com/eserver/zseries/zos/bkserv/)
- Perform as many migration actions as possible for IBM® middleware, IBM applications,
and ISV products that run on the existing (old) system. These
migration actions were identified in Step 1.
Reference information: IBM product publications and ISV
publications.
- Build, test, and put the old target system back into production.
Follow local procedures.
|