How the take back function works

z/OS DFSMShsm Implementation and Customization Guide
SC23-6869-01

When an original host is re-enabled to perform its unique responsibilities (through a restart or by leaving emergency mode), the take back process begins. The take back process involves the following procedures:
  • The promoted host recognizes that the original host is enabled and gives up the responsibilities that it took over.
  • Until the promoted hosts give them back, the original host does not perform any of the responsibilities that were taken over by the promoted hosts.

The following scenarios pertain to the take back function: