Error description

  • An asynchronous log reader task started for incremental updates
    for IBM DB2 Analytics Accelerator using Integrated
    Synchronization was terminated with DSNI092I TIMEOUT CAUSED
    TERMINATION OF ASYNCHRONOUS LOG READER TASK after a lock timeout
    DSNT376I on a needed resource. This could cause the distributed
    thread from the accelerator with
    WORKSTATION=Integrated-Synchronization to remain active until it
    is cancelled with the FORCE option. As long as the hung thread
    is not cancelled it will also prevent Db2 to be stopped
    successfully.
    IDAAV7R5/K
    

Local fix

  • n/a
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * All Db2 12 for z/OS users who use IBM Db2                    *
    * Analytics Accelerator with Integrated                        *
    * Synchronization as replication method.                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * An asynchronous log reader task                              *
    * terminated with DSNI092I TIMEOUT                             *
    * CAUSED TERMINATION OF ASYNCHRONOUS LOG                       *
    * READER TASK after a lock timeout                             *
    * DSNT376I on a needed resource. This                          *
    * could leave the distributed thread                           *
    * suspended which also prevented Db2                           *
    * to be stopped successfully.                                  *
    * Asynchronous log reader tasks may show                       *
    * a delayed termination processing when                        *
    * the Db2 member is stopped.                                   *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply corrective PTF when available                          *
    ****************************************************************
    When an asynchronous log reader task was terminating it tried
    to determine a log restart position which could run into a lock
    timeout. In that case the task was terminated by the watchdog
    process but the connection from IBM DB2 Analytics Accelerator
    identified by WORKSTATION=Integrated-Synchronization was never
    notified of the termination and the thread remained suspended.
    The thread had to be cancelled with the FORCE option before DB2
    could be stopped.
    Asynchronous log reader tasks were only terminating when the
    DBM1 address space was starting to terminate, which could see
    some delay after the -DB2 STOP DB2 command.
    Additional keywords: IDAAV7R5/K
    

Problem conclusion

  • Code has been changed to avoid locks during termination
    processing of asynchronous log reader tasks and threads from
    IBM DB2 Analytics Accelerator will not be suspended to wait
    for termination of the asynchronous log reader task.
    Asynchronous log reader tasks will terminate immediately after
    the -DB2 STOP DB2 command has been issued.
    

Temporary fix

Comments

APAR Information

  • APAR number

    PH23895

  • Reported component name

    DB2 OS/390 & Z/

  • Reported component ID

    5740XYR00

  • Reported release

    C10

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2020-03-31

  • Closed date

    2020-05-15

  • Last modified date

    2020-06-01

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

    UI69536

Modules/Macros

  • DSNILGRT DSNLJEMG DSNLJMCF DSNILGWD DSNLJMLR DSNTDSTE
    

Fix information

  • Fixed component name

    DB2 OS/390 & Z/

  • Fixed component ID

    5740XYR00

Applicable component levels

  • RC10 PSY UI69536

       UP20/05/23 P F005

Fix is available

  • Select the PTF appropriate for your component level. You will be required to sign in. Distribution on physical media is not available in all countries.

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSEPEK","label":"Db2 for z\/OS"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Line of Business":{"code":"LOB10","label":"Data and AI"}}]

Document Information

Modified date:
02 June 2020