Error description

  • In Graphical Assignment (GA) grey bars are used to show
    assignments for WO outside the selected set of WO defined by
    the Work List's Work Queries.    Clicking on the grey bars
    while holding down the Alt key (Alt-Left click) will display a
    dialog with basic information about the WO.
    
    But Right Clicking the bar will not display the standard Right
    Click menu or at least the Go To Work Order Tracking option.
    
    The Right Click menu has never been implemented for grey
    assignment bars in any version.
    
    STEPS TO REPRODUCE:
    1. Go to the Calendars application and select the Day calendar.
    2. If the End Date is not the end of next year, change it and
    Save.
    3. Define/Apply Shifts - select DAY shift and apply it to the
    entire length of the calendar.
    4. Go to WOTrack and create a new WO.  Give it a Wonum of DPC1
    and a Duration of 5.
    5. On the Plans tab give it Planned Labor of ELECT Firstclass.
    6. On the Assignments tab use the Available Labor to assign it
    to Liberi.
    7. Make another new WO, wonum DPC2, duration 5.   Planned Labor
    of ELECT Firstclass.      Save.
    8. Go to GA.    Create a new Work List.
    9. Use Calendar DAY, Shift DAY.
    10. Create a Work Query to select only wonum  DPC2:
               wonum = 'DPC2'
    11. Save and click on the Assignments tab.
    12. You will see a grey bar on the row for Liberi representing
    the assignment made for WO DPC1.
    13. Alt-Left click that grey bar and you will information for
    DPC1.
    14.  Right click on the grey bar and nothing will happen.
    15. Right click on the orange bar on the ELECT row, the Planned
    Labor for DPC2, and you will see a menu where one of the
    options is Go To Work Order Tracking.
    
    RESULTS:
    The Right Click menu appears for the orange bar but not for the
    grey bar.
    
    EXPECTED RESULTS:
    The Right Click menu should appear for the grey bar.   It may
    not have alll the options as for the orange bar but it should
    have at least Go To Work Order Tracking.
    
    VERSION INFORMATION:
    All Maximo versions
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Assignment application in Scheduler   *
    * 7.6.7.                                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * IN GRAPHICAL ASSIGNMENT THE RIGHT CLICK - GO TO              *
    * WOTRACKFUNCTION FOR GREYED OUT ASSIGNMENTS IS MISSING.       *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been made.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ16490

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2019-05-29

  • Closed date

    2019-06-05

  • Last modified date

    2019-06-05

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]