IJ12477: GSLP - THE CRITICAL PATH HIGHLIGHT COLORS ARE CONSIDERING THE NON WORK TIME AT FLOAT CALCULATION

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • PROBLEM: GSLP - The Critical Path highlight colors are
    considering the Non work time at FLOAT calculation when the
    records are Not Interruptible
    PERFORMANCE ISSUE: NO
    PRE CONDITIONS:
    - Create one Work Order with 6 tasks 2 hours each
    - Use a Shift of 8 hours per day
    - Link all tasks as predecessors
    STEPS TO REPRODUCE:
    - Go to Graphical Scheduling Large Project application
    - Open an existing record with the 8 hours shift and the work
    Order with tasks and move to Graphical View
    - Click at the CPM button
    CURRENT ERRONEOUS RESULT:
     The 6 tasks get align but just 2 get highlighted for the
    Critical PATH
    EXPECTED RESULT:
    As is working for Interruptible Work all 6 should be
    highlighted. Removing the Non working time from FLOAT.
    ADDITIONAL INFO: NO
    ENVIRONMENT (SYSTEM INFO):
    App Server  IBM WebSphere Application Server 9.0.0.7
    Version  Tivoli's process automation engine
    7.6.1.0-IFIX20181107-1300 Build 20180718-1141 DB Build V7610-83
    IBM Maximo Asset Management Work Centers 7.6.0.4 Build
    20180712-1824 DB Build V7604-119
    IBM Maximo Calibration 7.6.0.0 Build 20180718-1141 DB Build
    V7600-06
    IBM Maximo for Aviation 7.6.8.0 Build 20181113-2334 DB Build
    V7680-22
    IBM Maximo Asset Management Scheduler 7.6.7.2 Build
    20181114-1711 DB Build V7672-23
    IBM TPAE Integration Framework 7.6.1.0 Build 20180717-1722 DB
    Build V7610-02
    IBM Maximo Asset Management Scheduler Plus 7.6.7.1 Build
    20180718-1141 DB Build V7671-01
    IBM TPAE OS/REST Framework 7.6.1.0 Build 20180718-1141 DB Build
    V7610-38
    IBM Maximo Asset Management 7.6.1.0 Build 20180718-1141 DB
    Build V7604-01
    IoT Connection Utility 7.6.0.1 Build 20180709-1524 DB Build
    V7601-02
    Server OS  Windows Server 2012 R2 6.3
    Server DB  DB2/NT64 10.5 (SQL10058)
    

Local fix

  • Set the Work as Interruptible
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Scheduling Large Projects application *
    * in Scheduler 7.6.7.                                          *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * THE CRITICAL PATH HIGHLIGHT COLORS ARE CONSIDERING THE NON   *
    * WORK TIME AT FLOAT CALCULATION                               *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been delivered.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ12477

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2019-01-02

  • Closed date

    2019-01-14

  • Last modified date

    2019-01-14

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R767 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]