IBM Support

IJ12014: "MOVED TO TODAY" OPTION DO NOT MOVE TASKS IN GS FOR LARGE PROJECTS

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • Problem Description
    When moving a work order, its associated tasks do not move in
    Graphical Scheduling - Large Projects application
    
    
    
    STEPS TO REPRODUCE:
    1. Go to the Job Plans application
    2. Create a job plan with 2 tasks. e.g. task 10 and task 20
    Change the status to ACTIVE
    3. Go to the Work Order Tracking application.
    Create 3 work orders and attach the same job plan from above
    e.g. work orders  WOLP1 , WOLP2 , WOLP3
    4. Enter a description in the Description field e.g. Test.
    Set the Duration field 6 hours
    Save the record
    5. Go to Graphical Scheduling - Large Projects application
    6. Create a new schedule
    Populate the required fields
    Enter the work query below:
    wonum in ('WOLP1','WOLP2','WOLP3')
    7. Go to "Graphical View" tab
    The 3 work orders shows up in "Graphical View" tab
    8. Filter for  WOLP1  in the  Work  column to bring
    up the parent and task work orders for work order  WOLP1 .
    Task 10 and task 20 are displayed along with the parent work
    order
    9. Right click on the Parent work order bar on the Gantt Chart.
    Select  Move to Today  option
    The parent work order have been moved to today's date.
    But the task work orders have not been moved.
    
    
    
    RESULTS: When  move to today  option is selected, task
    work orders do not move with parent work order
    
    
    
    EXPECTED RESULTS:  Task work orders should move with parent
    work order
    
    
    
    REPORTED IN VERSION
    Maximo Asset Management 7.6.1 with Scheduler 7.6.7.1
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Scheduling Large Projects             *
    * application.                                                 *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * "MOVE TO TODAY" OPTION DO NOT MOVE TASKS IN GS FOR LARGE     *
    * PROJECTS.                                                    *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been delivered to the stream.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ12014

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2018-12-08

  • Closed date

    2018-12-10

  • Last modified date

    2018-12-10

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R767 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
10 December 2018