IJ03627: % COMPLETE IS NOT CALCULATING PROPERLY IN GRAPHICAL SCHEDULING WHEN CALCULATION METHOD IS SET TO TASK.

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • Steps to reproduce issue in Maximo 7.6.0.9 with Scheduler 7.6.7:
    
    STEPS TO REPRODUCE:
    
    Before testing Open Graphical Scheduling, open configure Gantt
    View Properties, default settings. Under the system properties
    section, make sure that PCTASKCOMP, PCACTHRS and PCPHYS are
    selected.
    
    1) Create a new work order
    
    2) Add 5 tasks to the work order:
    10: 2 hours
    20: 1 hours
    30: 1.5 hours
    40: 4 hours
    50: 2 hours
    
    3) Set task 20 to COMP by changing it's status under the task
    section.
    
    4) Create a new scheduler record, add shift and calendar as
    needed, add the new work order created earlier.
    
    5) On the Schedule tab, select the More information sub tab
    change the percent complete method so that it uses TASK
    
    6) Calculate % complete
    
    Open the Graphical View tab, since task 20 is complete it
    should show 100 % and there should be a percentage rolled up to
    the work order header, that did not happen in this case.
    

Local fix

  • n/a
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Summary roll ups for various % complete methods were not     *
    * working correctly                                            *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • Fixed
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ03627

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2018-01-25

  • Closed date

    2018-01-29

  • Last modified date

    2018-01-29

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

  • R767 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
29 January 2018