Add Resource CRQ Activity (ADDRSCCRQA)

The Add Resource Change Request Activity (ADDRSCCRQA) command adds an activity to a change request description which performs an IPL of a managed iSeries system or restarts a non-iSeries resource such as a PS/2 with NetView DM/2 installed.

Restrictions:

  1. You must have *CHANGE authority to the change request description and *EXECUTE to the library.
  2. A resource other than *SYSx is not supported for iSeries managed systems.
  3. If a value for NODL is specified, the node list can only contain entries that have a value of *SNA for the address type.
  4. Keylock must be in NORMAL position or the request is rejected.

Notes:

The following notes provide information on how the command works.

  1. Authorization to the product specified on the activity is not verified until the activity runs.
  2. All conditions must be satisfied before the activity can run.
  3. The start times indicate when the activity can be started. Actual start times can be later due to network and system delays.

Parameters

Keyword Description Choices Notes
CRQD Change request description Qualified object name Required, Positional 1
Qualifier 1: Change request description Name
Qualifier 2: Library Name, *LIBL, *CURLIB
ACTIVITY Activity Name, *GEN, *LAST Optional, Positional 2
ACTION Action *RESTART Optional, Positional 3
RSC Resource Name, *SYS, *SYSA, *SYSB Optional
NODL Managed systems node list Element list Optional
Element 1: Node list Single values: *NONE
Other values: Qualified object name
Qualifier 1: Node list Name
Qualifier 2: Library Name, *LIBL, *CURLIB
CPNAME Managed system node names Single values: *NONE
Other values (up to 50 repetitions): Element list
Optional
Element 1: Network identifier Communications name, *NETATR
Element 2: Control point Character value
OPTION How to end *CNTRLD, *IMMED Optional
DELAY Delay time, if *CNTRLD 0-65535, 3600 Optional
TEXT Text 'description' Character value, *GEN Optional
COND Activity conditions Single values: *NONE
Other values (up to 5 repetitions): Element list
Optional
Element 1: Activity Generic name, name, *PRV
Element 2: Relational operator *EQ, *GT, *LT, *LE, *NE, *GE
Element 3: End code 0-99, *SUCCESS, *FAIL, *NOTRUN, *ANY
Element 4: Condition mode *ALLNODES, *SAMENODE
STRTIME Activity start time Element list Optional
Element 1: Start after Element list
Element 1: Time Time, *CURRENT
Element 2: Date Date, *CURRENT, *NEXT
Element 2: Start before Element list
Element 1: Time Time, *ANY, *CURRENT
Element 2: Date Date, *ANY, *CURRENT, *NEXT
RMTSTRTIME Start time on managed system Element list Optional
Element 1: Time zone *LCLSYS, *MGDSYS
Element 2: Start after Element list
Element 1: Time Time, *CURRENT
Element 2: Date Date, *CURRENT, *NEXT
HOLD Hold activity *NO, *YES Optional

Change request description (CRQD)

Specifies the change request description object name.

The possible library values are:

*LIBL
All of the libraries in the user and in the system portions of the job's library list are searched.
*CURLIB
The current library for the job is used to locate the object.
library-name
Specify the name of the library to be searched.

The possible change request description value is:

change-request-description
Specify the name of the change request description object.

Activity (ACTIVITY)

Specifies the name of the activity to add to the change request description.

*GEN
An activity name is generated. The activity name is of the form QACTxxxxxx, where xxxxxx is the first multiple of ten not already being used.
*LAST
The activity is the last to run in the change request. When *LAST is specified for the activity (ACTIVITY) parameter, the condition (COND) parameter and the start time (STRTIME) parameter cannot be specified. Only one activity named *LAST can exist in the change request description.
activity-name
Specify a 10-character activity name.

Action (ACTION)

Specifies the functions to be performed on the resource.

*RESTART
Use to restart the specified resource. If the resource specified is *SYS, *SYSA, or *SYSB, the managed system stops and restarts.

Resource (RSC)

Specifies the resource name.

*SYS
The action is performed against the entire system. For the restart action, this means that the managed system is powered down and restarted. The system panel determines the IPL source.
*SYSA
This is the same as *SYS except the IPL source is the A side.
*SYSB
This is the same as *SYS except the IPL source is the B side.
resource-name
Specify a 16-character resource name on the managed system. This value is not supported by iSeries managed systems.

Managed systems node list (NODL)

Specifies that the node list parameter is the object name that contains a list of systems which are the destinations for the activity. This parameter cannot be specified if the control point name (CPNAME) parameter is also specified.

The possible value is:

*NONE
The systems on which this activity is to be performed are not specified by a node list. Individual control point names must be specified.

The possible library values are:

*LIBL
All of the libraries in the user and system portions of the job's library list are searched for the node list object.
*CURLIB
The current library for the job is used to locate the node list object.
library-name
Specify the name of the library to be searched.

The possible node list name value is:

node-list-name
Specify the node list object name containing the list of systems on which the activity is to be performed.

Managed system node names (CPNAME)

Specifies the APPN control point names of the managed systems on which this activity is performed. Control point names cannot be specified if a node list is specified.

*NONE
The systems on which this activity is performed are not identified individually. A node list must be specified.

The possible values are:

*NETATR
The network ID of the local system is used. This is useful when the node being specified is in the same network as the local system.
network-identifier
Specify the APPN network identifier of the managed system on which the activity is performed.

The possible control point name value is:

control-point-name
Specify the APPN control point name of the managed system on which the activity is to be performed. For NetView Distribution Management Agents, the control point name is the change control client which supports numeric characters (0-9) in the first position of control point names that are valid in other platforms.

How to end (OPTION)

Specifies how to end. It specifies whether the system allows the active subsystems to end processing of active jobs in a controlled manner, or whether the system ends the job immediately.

*CNTRLD
The jobs are ended in a controlled manner. If the jobs cannot be ended in a controlled manner during the delay period, they are ended immediately.
*IMMED
Jobs are ended immediately.

Delay time, if *CNTRLD (DELAY)

Specifies the number of seconds the system waits for the jobs to be ended in a controlled manner.

3600
The system waits one hour before ending the jobs immediately.
delay-time
Specify the delay time in seconds.

Text 'description' (TEXT)

Specifies the activity description.

*GEN
A description is generated.
text-description
Specify a 50 character description of the activity.

Activity conditions (COND)

Specifies which conditions must be met before this activity can be performed. Each condition identifies an activity which must be run before this activity and the value the end code from that activity must have to allow this activity to run. The default condition is that the previous activity (in alphabetical order) must complete successfully before this activity can be run.

The possible single value is:

*NONE
There are no conditions for this activity.

The possible conditioning activity values are:

The activity which must be run before this activity.

*PRV
This activity is conditioned on the previous activity. Activities are ordered alphabetically by activity name. If the activity being added is the first activity, a previous activity does not exist and any condition with *PRV is marked as having been met.
conditioning-activity-name
Specify the name of the activity which must be run before this activity. The activity name specified in the activity (ACTIVITY) parameter cannot be specified in the conditioning activity name. An activity cannot be conditioned on itself.
generic*-activity-name
Specify the generic name of the activities which must run before this activity.

The possible relational operator values are:

This element is the relational operator to use when comparing the end code from the conditioning activity.

*EQ
Equal
*GT
Greater than
*LT
Less than
*NE
Not equal
*GE
Greater than or equal
*LE
Less than or equal

The possible condition code values are:

*SUCCESS
The activity ended successfully (0 <= end code <= 9). This end code can only be specified with relational operator *EQ or *NE.
*FAIL
The activity failed (10 <= end code <= 89). This end code can only be specified with relational operator *EQ or *NE.
*NOTRUN
The activity is never started (90 <= end code <= 99). This end code is only specified with relational operator *EQ or *NE.
*ANY
The activity ended with any end code. This end code is only specified with the relational operator *EQ.
end-code
Specify an integer value (0-99) that indicates the result of an activity (success or failure). The end code ranges and descriptions are:
00
Activity completed successfully.
01-09
Activity completed with warning messages.
10-29
Activity did not complete successfully.
30-39
Activity was canceled by a user before it completed.
  • 30 = Activity ended with *CNTRLD option
  • 35 = Activity ended with *IMMED option
  • 39 = Activity ended with *FRCFAIL option
40-49
Activity was not run due to errors detected by the application.
  • 40 = Activity not run for security reasons
90-99
Activity was not run because conditions or schedules were not met.
  • 95 = Scheduled start time expired
  • 99 = Conditions cannot be met

The possible condition mode values are:

This element indicates which systems the conditioning activity must have completed on before this activity can be performed.

*ALLNODES
The conditioning activity specified must complete on all nodes before this activity runs.
*SAMENODE
When the conditioning activity specified completes for a given node, the activity specified on the ACTIVITY parameter may run for that same node even though the conditioning activity specified may not have completed for all other nodes. In the case where this activity lists a node not in the conditioning activity, this activity may run for that node; the condition is ignored.

Activity start time (STRTIME)

Specifies the date and time when this activity can be started on the central site system. The current date and time values and next date values are determined when the change request is submitted.

The possible start after time values are:

*CURRENT
This activity can start any time on or after the time when the change request is submitted.
start-after-time
Specify the time when this activity can start. The time can be entered as 4 or 6 digits (hhmm or hhmmss) where hh = hours, mm = minutes, and ss = seconds. Seconds are optional. The time can be specified with or without a time separator such as a colon (:). With a time separator, specify a string of 5 or 8 digits (hh:mm or hh:mm:ss).

The possible start after date values are:

*CURRENT
This activity can start on or after the date on which the change request is submitted.
*NEXT
The activity can start on any date after the date when the change request is submitted.
start-after-date
Specify the date after this activity can start. The date must be specified in the job date format.

The possible start before time values are:

This element is ignored if the start before date is *ANY.

*ANY
The activity can start at any time on or before the start before date.
*CURRENT
The activity must start before the time when the change request was submitted on the date specified on the start before data element. This value cannot be specified if the start before date is *CURRENT.
start-before-time
Specify the time before the activity must start. If the activity cannot be started before this time, it never starts. The time can be entered as 4 or 6 digits (hhmm or hhmmss), where hh = hours, mm = minutes, and ss = seconds. Seconds are optional. The time can be specified with or without a time separator such as a colon (:). With a time separator, specify a string of 5 or 8 digits (hh:mm or hh:mm:ss).

The possible start before date values are:

*ANY
The activity can start at any time after the start after time and the start after date.
*CURRENT
The activity must start on the date the change request is submitted.
*NEXT
The activity must start by the day after the date the change request is submitted.
start-before-date
Specify the date before the activity must start. If the activity cannot be started by this date, it never starts. The date must be specified in the job date format.

Start time on managed system (RMTSTRTIME)

Specifies the date and time when the activity can begin running on the managed system. The current date and time values and next date values are determined when the activity begins running on the central site system based on the central site date and time.

The possible time zone values are:

*LCLSYS
The remote start time is specified in the time zone of the central site system.
*MGDSYS
The remote start time is specified in the time zone of the managed system.

The possible start after time values are:

This is the definition of the time when the activity is to start.

*CURRENT
This function can start on the managed system at any time on or after the time this activity is started on the central site system on the date specified in element 3.
start-after-time
Specify the time when this function can start on the managed system. The time can be entered as 4 or 6 digits (hhmm or hhmmss) where hh = hours, mm = minutes, and ss = seconds. Seconds are optional. The time can be specified with or without a time separator. With a time separator, specify a string of 5 or 8 digits (hh:mm or hh:mm:ss).

The possible start after date values are:

*CURRENT
This function starts on the managed system on any date on or after the activity starts on the central site system.
*NEXT
This function starts on the managed system on any date after the activity starts on the central site system.
start-after-date
Specify the date after the functions start on the managed system. The date must be specified in the job date format.

Notes

  1. The special values *CURRENT and *NEXT are specified for the date and the time if the time zone value *MGDSYS is specified.
  2. This parameter can only be specified if *RUN or *SNDRUN actions are specified.

Hold activity (HOLD)

Specifies that the activity be held when the change request is submitted.

*NO
The activity is not held and it runs when all conditions and the start time are met.
*YES
The activity is held for all nodes when the change request is submitted. It must be released by a user before it will run.

Examples

Example 1: Adding an Activity

ADDRSCCRQA   CRQD(MYLIB/CR1)  ACTIVITY(ACT01)
             ACTION(*RESTART)  RSC(*SYS)
             STRTIME((04:00:00 *NEXT))
             NODL(NETLIB/STORES)

This command adds an activity to re-IPL the store systems at 4:00 a.m. tomorrow. These store systems are identified in the STORES node list.

Example 2: Performing an IPL

ADDRSCCRQA   CRQD(MYLIB/CR1)  ACTIVITY(ACT01)
             ACTION(*RESTART)  RSC(*SYSA)
             CPNAME((*NETATR SYS1))  OPTION(*IMMED)

This command adds an activity to perform an IPL of the system SYS1 immediately to the A side.

Error messages