Precautions when Scheduling Customized Weekly Activity

If you customize control group weekly activity and also schedule backups late at night, you need to make sure the backup completes before the start of the next day. Scheduling delays could cause the backup control group to run later than scheduled, resulting in missed saves. Assume the following backup control group is scheduled to run nightly at 23:00.

                   Display Backup Control Group Entries              RCHAS400   
                                                                                
 Group . . . . . . . . . . : SAMPLE                                             
 Default activity  . . . . : *BKUPCY                                            
 Text  . . . . . . . . . . : Create sample backup control group                 
                                                                                
                         Auxiliary   Weekly    Retain  Save      SWA            
       Backup      List  Storage     Activity  Object  While     Message        
 Seq   Items       Type  Pool Device SMTWTFS   Detail  Active    Queue          
   10  *EXIT                         *DFTACT                                    
   20  LIB1              *SYSBAS           F   *NO     *NO                      
   30  LIB2              *SYSBAS     FIIIIII   *NO     *NO                      
   40  *EXIT                         *DFTACT                                    
                                                                                
                                                                                
                                                                                
                                                                                
                                                                                
                                                                                
                                                                         Bottom 
 Press Enter to continue.                                                       
                                                                                
 F3=Exit   F11=Display exits   F12=Cancel   F14=Display client omit status      

Suppose that the job scheduler submits the control groups to the same job queue that is used by the month-end batch job such that this backup control group does not start running on Saturday night as 23:00, but on Sunday morning as 00:00:03. When the backup starts to run, BRMS will retrieve the current date and because it is Sunday instead of Saturday, the following occurs:

You can easily avoid these problems by ensuring that the batch job queue allows more than one job to process, or use different batch job queues.