Supported version: Microsoft Project versions 2007, 2010, and 2013 are supported for import and export.
To import a plan, save the Microsoft Project file as a XML file and import the XML file. When you export a plan, an XML file is generated that you can open in Microsoft Project. Only the functions and attributes of Microsoft Project that are supported by your plan are imported or exported.
Mapping replaces a task type or resource from Microsoft Project with a supported work item type or resource in your target project. When you import a project plan, you can map the task types from Microsoft Project to the work item types in your project.
When you map task types, the attributes of task types in Microsoft Project are replaced with the attributes of the supported work item types in your target project. For example, you might map a task of type Summary Task from Microsoft Project to a Task work item type in your project.
The following tables illustrate how the resources and attributes of Microsoft Project map to the resources and attributes of your application.
Microsoft Project Plan | Your existing plan |
---|---|
User | Contributor |
Summary Task | Any work item type |
Task | Any work item type |
Task Assignment | The mapped user is assigned as the owner of the work item. |
Project | Plan |
Dependency | If you are using the Formal Project Management process, the Finish-to-Start dependency is imported and mapped to the Finish-to-Start dependency type. Other dependencies are not imported or mapped. In processes where no dependencies are defined, such as Scrum, dependencies are not imported or mapped. |
Constraints | If you are using the Formal Project Management process, the As soon as possible, Start no earlier than, and Finish no later than constraints are imported and mapped to the same constraints. For Start no earlier and Finish no later than constraints, the constraint dates are also imported. Other constraints are not imported or mapped. In processes where no constraints are defined, such as Scrum, constraints are not imported or mapped. |
Constraints and dependencies
The import and export capabilities in your application support the Finish-to-Start dependency among tasks in Microsoft Project. The remaining dependencies in Microsoft Project are not imported. Similarly, the import and export capabilities support only the As soon as possible, Finish no later than, and Start no earlier than constraints. The remaining constraints in Microsoft Project are not imported.
Task with multiple assignments
A task that has multiple assignments in Microsoft Project is imported into your project as a parent Summary Task and child tasks. For example, a task in Microsoft Project is assigned to Resource1, Resource2, and Resource3. When the task is imported to the target project, a Summary Task named T1 is created with three child tasks: T1_Task1, T1_Task2, and T1_Task3. As a result, Resource1 is assigned to T1_Task1, Resource2 is assigned to T2_Task2, and Resource3 is assigned to T1_Task3.
Your existing plan | Microsoft Project Plan |
---|---|
Project and iteration plans | Project |
Contributor | User |
Leaf work - items | Task |
Non leaf work - items | Summary Task |
Dependency and Constraints | Dependency and Constraints |
Assignment | Assignment |
Watch videos CLM playlistJazz.net channel User Education channel |
Learn more CLM learning circleAgile learning circle Learning circles |
Ask questions Jazz.net forumdeveloperWorks forums |
Get support Support PortalDeployment wiki Support blog |