Parallel testing

If you want to perform the migration and then continue immediately into parallel testing in a job-tracking environment,you can use the following procedure as a guide. However, you should carefully consider the applicability of this procedure in your own Tivoli Workload Scheduler for z/OS configuration.

  1. Stop your production system.
  2. Perform data set conversion and copying.
  3. Start your production system.
  4. |Start Tivoli Workload Scheduler for z/OS, Version 8.6.

You should also consider:

Using the preceding notes as a guide, you will be able to run one production system and one Tivoli Workload Scheduler for z/OS test system in parallel. The work with the database dialogs and the long-term-planning functions can be fully tested this way. The job-tracking functions of the test system will be incomplete because only the specially created test jobs will be submitted by the test system. However, the tracking of work, including the tracking of applications and jobs in the production area, will be done normally.