Migration considerations
IBM® attempts to make the installation of new releases as easy as possible. Initially, you should install Tivoli Workload Scheduler for z/OS without taking any customization actions in order to achieve a stable environment. Refer to the Program Directory for specific instructions about using System Modification Program/Extended (SMP/E) to install Tivoli Workload Scheduler for z/OS.
You can migrate from or fall back to previous releases without IPLing z/OS.
|The following are some migration considerations and, |in some cases, necessary prerequisite steps to perform, before migrating |to the current release, to ensure a proper fallback migration can |be performed, if necessary at any time.
|-
|
- If you are performing a fallback because of problems experienced |on Tivoli Workload Scheduler for z/OS, be sure to keep the Tivoli Workload Scheduler for z/OS data sets for diagnostic |purposes. |
- If you migrate to and fallback from Tivoli Workload Scheduler for z/OS to test the environment |before your official migration, ensure that |you reallocate all Tivoli Workload Scheduler for z/OS data sets before the next migration exercise. |
- |Before you migrate to Tivoli Workload Scheduler for z/OS Version 8.6 from |Version 8.2, ensure you have applied at least the fix for APARs PK24633 |and PK24711 on version 8.2. This is required to successfully perform |a fallback migration from Tivoli Workload Scheduler for z/OS Version 8.6 to version |8.2, if necessary at any time.| |
- |If you are migrating from Tivoli Workload Scheduler for z/OS Version 8.2 to Version |8.6, note that the default value of the GDGNONST parameter |has been changed from NO to YES. Refer to the OPCOPTS initialization |statement in Customization and Tuning for more information about the GDGNONST parameter.| |
- |If you are migrating from version 8.2 to version 8.5.1 |or from version 8.2 to 8.6, and you have not applied the fix for APAR |PK36095 on your version 8.2 installation, then ensure you set TASKUSER(NO) to |maintain the current behavior of your environment. With version 8.5.1 |and later, the default value for TASKUSER is YES. |Refer to the OPCOPTS initialization statement in Customization and Tuning for |more information about the TASKUSER parameter.| |
- |If you are migrating from version 8.2 to version 8.5.1 |or from version 8.2 to 8.6, and you have not applied the fix for APAR |PQ85880 on your version 8.2 installation, be aware that the default |setting of the CODEPAGE keyword in the SERVOPTS initialization |statement continues to be IBM-137, however, for version 8.5.1 and |later, if you specify a codepage value different from the default |value, a check has been implemented to use the default codepage if |the first four characters of the codepage you specify are different |from "IBM-". Refer to the SERVOPTS initialization statement |in Customization and Tuning for more information about the CODEPAGE parameter.| |
- |Before you migrate to Tivoli Workload Scheduler for z/OS Version 8.6 from |Version 8.5.1, ensure you have applied at least the fix for APAR PM14386 |on version 8.5.1. This is required to successfully perform a fallback |migration from Tivoli Workload Scheduler for z/OS Version 8.6 to version 8.5.1, |if necessary at any time.| |
- |The handling of operations in X status in a plan has
|changed beginning with version 8.5.1 and later. A migration operation
|is interrupted if an operation in X status is found in the current
|plan. Message EQQIC51E is issued. Before retrying the migration, perform
|the following steps, depending on the scenario you are running:
|
-
|
- A migration from Version 8.5 to either Version 8.5.1 |or 8.6 |
- If conditions have been defined and used in the plan, then check
|if you need the X status propagation to normal successors or, the
|new logic that makes the normal successor ready is preferred. If you
|require X status propagation, complete these steps:
|
-
|
- Change in AD the normal dependencies in conditions ST=C. Refer |to the information about conditional logic in Managing the Workload. |
- Wait until the occurrences involved in these definitions complete |in the Plan. |
- Perform a replan to remove these instances.
| - A fallback from either Version 8.6 or 8.5.1 to version |8.5 |
- If conditions have been defined and used in the plan, check
|if you used the new logic that makes the normal successor ready. Consider
|that after the fallback, they will become X. If you used the new logic
|for X status, then perform the following steps:
|
-
|
- Change in AD the definitions so that the new logic is not used. |
- Wait until the occurrences involved in these definitions complete |in the Plan. |
- Perform a replan to remove these instances.
|