Ensuring that all installation tasks are complete
Check that you have:
- Created a started-task procedure for the controller
- Allocated data sets
- Given security authority to the started task to access its data sets
- Specified the initialization statements in the parameter library (EQQPARM)
- Included the controller in an XCF group, if it uses an XCF connection
- Defined a VTAM® application ID for the controller and activated the VTAM resources, if it uses an NCF connection
- Updated SYS1.PARMLIB and defined VTAM resources, if users communicate with the controller through the Tivoli Workload Scheduler for z/OS API or if the Tivoli Workload Scheduler for z/OS server is used.
- Set up the ISPF environment for Tivoli Workload Scheduler for z/OS dialog users.