While you are in the middle of creating or modifying a scheduling environment, you can take this shortcut method to create new resources. In this case where you wanted to create the new VECTOR resource and add it to DB2LATE, this method would be the logical choice.
From either the Create a Scheduling Environment panel or the Modify a Scheduling Environment panel (they look very similar), enter an A on any Action line, as shown in Figure 1.
Scheduling-Environments Notes Options Help
-------------------------------------------------------------------------
IWMAPAJ Modify a Scheduling Environment Row 1 to 2 of 2
Command ===> ____________________________________________________________
Scheduling Environment Name DB2LATE_________ Required
Description . . . . . . . . . Offshift DB2 Processing_________
Action Codes: A=Add D=Delete
Required
Action Resource Name State Resource Description
__ DB2A ON______ DB2 Subsystem
a_ PRIMETIME OFF_____ Peak Business Hours
This would take you to the Resource Definition List panel, where you can enter an A on any Action line, as shown in Figure 2. (Alternately, you can enter a / next to the resource names and then put the cursor under the Resources field at the top of the screen and press Enter. Then select 1 from the options in the pop-up box.)
Resources Notes Options XREF Help
------------------------------------------------------------------------
IWMAPAS Resource Definition List Row 1 to 4 of 4
Command ===> ___________________________________________________________
Selection For Scheduling Environment DB2LATE
Action Codes: A=Add S=Select X=XREF /=Menu Bar
Action Resource Name In Use Resource Description
__ CICS001 YES CICS Subsystem
__ DB2A YES DB2 Subsystem
__ IMS1 YES IMS Subsystem
a_ PRIMETIME YES Peak Business Hours
As in the method described in Creating a new resource directly from the main panel, from here you'll go to the Define Resource panel (as was shown in Figure 3) to enter the new resource name and description.
When you come back to the Resource Definition List panel, you can now select the new VECTOR resource to be part of the DB2LATE scheduling environment, as shown in Figure 3.
Resources Notes Options XREF Help
------------------------------------------------------------------------
IWMAPAS Resource Definition List Row 1 to 5 of 5
Command ===> ___________________________________________________________
Selection For Scheduling Environment DB2LATE
Action Codes: A=Add S=Select X=XREF /=Menu Bar
Action Resource Name In Use Resource Description
__ CICS001 YES CICS Subsystem
__ DB2A YES DB2 Subsystem
__ IMS1 YES IMS Subsystem
__ PRIMETIME YES Peak Business Hours
s_ VECTOR Vector Processor
Having done that and exiting, you come back to the Modify a Scheduling Environment panel, as shown in Figure 4.
Scheduling-Environments Notes Options Help
-------------------------------------------------------------------------
IWMAPAJ Modify a Scheduling Environment Row 1 to 3 of 3
Command ===> ____________________________________________________________
Scheduling Environment Name DB2LATE_________ Required
Description . . . . . . . . . Offshift DB2 Processing_________
Action Codes: A=Add D=Delete
Required
Action Resource Name State Resource Description
__ DB2A ON______ DB2 Subsystem
__ PRIMETIME OFF_____ Peak Business Hours
__ VECTOR ON______ Vector Processor
Now the VECTOR resource name is part of the DB2LATE scheduling environment. As always, you need to specify either ON or OFF under the Required State. In this case, we chose ON.