Start of change
IXC583I
SYSTEM-MANAGED process FOR STRUCTURE strname LOGICAL STRUCTURE VERSION logicalver1 logicalver2 MAY BE DELAYED IN THE phase PHASE. REASON: reason AUTO VERSION: procid1 procid2

Explanation

A system-managed process has encountered a condition which may delay completion of the process.

In the message text:
process
One of the following:
REBUILD
A system-managed rebuild is in progress.
DUPLEXING REBUILD
A system-managed duplexing rebuild is in progress.
strname
The name of the structure.
logicalver1
First half of the logical structure version number.
logicalver2
Second half of the logical structure version number.
phase
One of the following
COPY
Copying of all required data from the old instance of the structure to the new.
reason
One of the following:
STRUCTURE OBJECTS IN STORAGE-CLASS MEMORY
Either of the following situations may exist:
  • Some structure objects have been migrated to storage-class memory and must be retrieved before the system-managed process can progress.
  • Some structure objects must be migrated to storage-class memory to provide space for new objects to be written to coupling facility storage.
AUTO VERSION
A unique value identifying the system-managed process being started. It can be used to correlate messages and XCF component trace records associated with the current system-managed process.
procid1
First half of the auto version.
procid2
Second half of the auto version.

System action

The system-managed process continues.

Operator response

None.

System programmer response

If the delay in completion of the system-managed process becomes excessive, you may choose to stop the process using the SETXCF STOP command.

Source

Cross System Coupling Facility (SCXCF)

Module

IXCL2ATC, IXCL2ATH

Routing code

Start of change*/2 Note 13End of change

Descriptor code

Start of change5/--End of change