z/OS MVS Planning: Global Resource Serialization
Previous topic | Next topic | Contents | Contact z/OS | Library | PDF


Steps in converting to a star complex

z/OS MVS Planning: Global Resource Serialization
SA23-1389-00

There are two phases to migration that you need to consider. They are:

  1. Migrating to the new release.

    If the installation does not plan to run a star complex after the new release is installed, re-IPL the system specifying GRS=JOIN to bring the system back into the ring complex. The only systems that should remain in the ring complex are systems connected to the coupling facility.

  2. Converting from a ring complex to a star complex.

Go to the previous page Go to the next page