z/OS MVS Planning: Global Resource Serialization
Previous topic | Next topic | Contents | Contact z/OS | Library | PDF


Backup considerations

z/OS MVS Planning: Global Resource Serialization
SA23-1389-00

A fully-connected complex with alternate links provides the option of using ring acceleration as well as a very high level of reliability. It does not, however, remove the IBM® 3088 as a potential single point of failure. Thus, IBM recommends that you provide an alternate 3088 to act as a backup. (Integrated CTC adapters can also act as backup connections between systems.)

In such a configuration, dedicate two data links from the primary 3088 and two data links from the alternate 3088 for each connection in your fully-connected complex. If a system runs on a processor that, like the 3090 Model 400E, can be partitioned, connect links from both 3088 units to both sides of the processor complex.

Go to the previous page Go to the next page




Copyright IBM Corporation 1990, 2014