Resource manager termination delay can be indicated by the following
WTOR messages:
- These messages can delay the termination of resource manager until
they receive a reply.
ATR225D CANCEL DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR226D MEMTERM DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR227D CANCEL DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR228D MEMTERM DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR229D CANCEL DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR230D MEMTERM DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR231D CANCEL DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR232D MEMTERM DELAYED. REPLY WAIT, BACKOUT, OR COMMIT TO RESOLVE
INDOUBT UR. URID=uridentifier
ATR233D CANCEL DELAYED. REPLY BACKOUT, OR COMMIT TO RESOLVE INDOUBT
UR. URID=uridentifier
ATR234D MEMTERM DELAYED. REPLY BACKOUT, OR COMMIT TO RESOLVE INDOUBT
UR. URID=uridentifier
- Task or memory termination of the resource manager address space
is delayed because of an outstanding transaction in the "in-doubt" state.
RRS forces the operator to manually resolve the "in-doubt" transaction
before allowing termination to continue.