Starting the target environment

Start the new environment, including the deployment manager, managed node or nodes, and servers.
Figure 1. Sample environment after the target is started. The source environment is not running. The target can read from the databases.
The details of the diagram are provided in the figure caption.

Procedure

  1. Start the target deployment environment:
    1. Start the deployment manager.
    2. Start the nodes and make sure that they are synchronized with the deployment manager.
      Important: If you have an environment with the Business Space component (for Process Portal) installed on multiple managed nodes in a cell, start only one node first and start the other nodes only after the first node has already started.
    3. Start the clusters.
  2. Check to make sure that all clusters, servers, and messaging engines have started.