This document describes the recommended strategy and steps for applying maintenance updates to IBM Connections 5.0. It includes important information on known issues.

Content


Table of Contents:

Before you begin
  • It's important that you read this document to understand the requirements and the steps to deploy the latest IBM Connections 5.0 cumulative refresh (CR). This document is a summary of requirements and procedures for installing the latest CR and not a step-by-step guide.
  • Make sure the Connections 5.0 CR is installed before attempting to upgrade the FileNet Content Engine Server & Client and FileNet Collaboration Services.

Section 1 - General Information


  • Updates for IBM Connections 5.0 are delivered via interim fixes called "Cumulative Refreshes" (CRs). CRs are cumulative. The latest CR will contain the changes included in all previous CRs. It is only necessary to install the latest CR to get all available changes.
  • Cumulative Refreshes (CRs) consist of a set of cumulative fixes, one for each IBM Connections application. The entire application is updated.
  • The CR includes multiple code changes bundled into a single package and verified together following IBM's interim fix delivery process.
  • We recommend customers to apply the latest set of CR fixes as it becomes available. This ensures that all the applications in the IBM Connections environment are at the latest version. This in turn prevents the occurrence of known issues in your environment, increasing stability and minimizing downtime. It also helps expedite the resolution of newly reported issues.

Section 2 - List of IC 5.0 CRs



1. IBM Connections 5.0 CR1 (Released October 2014)


2. IBM Connections 5.0 CR2 (Released February 2015)

3. IBM Connections 5.0 CR3 (Released June 2015)


4. IBM Connections 5.0 CR4 (Released March 2016)



Section 3 - Important Release Notes

  • When you upgrade a Connections 4.5 release to Connections 5.0, the index structure is the same between the two releases and the index can be migrated, avoiding the need to rebuild the search index fully. You should migrate the index as outlined in the Migrating the search index from the Connections 4.5 deployment to Connections 5.0 topic on the product documentation.
  • Existing IBM Connections environments using Oracle database that are migrating into IBM Connections 5.0 will need to use an updated SQL script. The updated script is found at this location:
    delta\native\connectionsSql_5.0.0.0_20150710_1845.zip\connections.sql\profiles\oracle\predbxfer45.sql
    <IC_INSTALLATION_DIR>/connections.sql/profiles/oracle/predbxfer45.sql

Section 4 - Software Requirements and Recommended Updates



Review this section for the software updates and requirements for your IBM Connections environment. The installation details are included in Section 5 - Instructions on applying Cumulative Refresh (CR) updates. For general requirements, please review the System Requirements for IBM Connections 5.0 document.

The following table lists specific configuration requirements per CR level:

  • IBM FileNet & IBM Connections 5.0 databases
    CR level IBM FileNet (if using CCM) Database Updates
    CR1 FileNet updates are required for each CR. See technote 1683147 for details.



    Activities, Blogs, Files, Forums, and Homepage database updates are required. See technote 1681028 for details
    CR2 Blogs, Communities, and Homepage database updates required. See technote 1694319 for details.
    CR3 Homepage database update required. See technote 19029441 for details
    CR4* No database updates
    * Note:There are no FileNet updates going from CR3 to CR4
  • Cognos Server Update for IC 5.0 CR

For Cognos, you are required to run the standalone wizard to upgrade the Cognos server from IBM Connections 5.0 to the CR1 level. There are no changes for the Cognos server after CR1. If you are upgrading directly to CR2 (and above) from IC 5.0, you must run the Cognos update wizard which will upgrade the Cognos server to the CR1 level. For additional details on upgrading the Cognos server refer to technote 1696033.

Download the Cognos Wizard from IBM Fix Central:
The following tables display recommended upgrades per CR level:


Miscellaneous recommended upgrades per CR levels:
  • CA SiteMinder Version 12.5.1 is the latest supported SiteMinder fix pack and recommended for IBM Connections 5.0 CR1 and above.

Section 5 - Instructions on applying Cumulative Refresh (CR) updates

Always install the latest Cumulative Refresh (CR), as it contains the changes from all previous CRs. CRs are cumulative. It is only necessary to install the latest CR to get all available changes. For example, CR2 contains all the changes from CR1 plus the new changes added in CR2.

Before you begin:

  • These instructions are a summary of the procedure. They are intended to complement the product documentation pages on installing fix packs, because CRs use the same installation process as a fix pack. Review the topics under the Updating IBM Connections 5.0 page for more details specifically Updating IBM Connections 5.0 with the latest Cumulative Refresh (CR)
  • IBM Connections 5.0 environments using Connections Content Management (CCM) will need to upgrade the FileNet installation as part of the upgrade to a 5.0 CR. IBM Connections environments that do not have CCM can follow these guides disregarding the FileNet sections. Here are Step-by-Step examples of applying a CR to IBM Connections 5.0 with CCM

Steps to install IBM Connections CRs

The installation of a 5.0 CR consist of the following steps:

  1. Upgrade WebSphere Application Server (optional but strongly recommended)
  2. Upgrade to the latest version of Install Manager
  3. IBM Connections CR installation
  4. Update Connections Databases
  5. Upgrade FileNet Components
  6. Update miscellaneous items

1. Upgrade WebSphere Application Server

If you need to apply WebSphere Application Server (WAS) fixes or fixpacks, we recommend you install these prior to updating Connections. Applying WAS fixes follow these general steps:

1. Stop WAS processes (deployment manager, node agents, nodes).

2. Apply all WAS fixes.

3. Restart WAS processes (deployment manager, node agents, nodes).

For detailed information on how to apply fixes and fix packs on WAS, review the Installing and uninstalling interim fixes and fix packs on distributed operating systems topics in the product documentation.


2. Upgrade to the latest version of the Installation Manager

Upgrade to the IBM Installation Manager 1.8. The latest version of the update installer is available from Fix Central via this link: IBM Installation Manager

3. Install IBM Connections CR

1. Download the latest CR update. The latest CR update is on IBM Fix Central. (You will find the direct link to the latest CR listed in Section 2 - List of IC 5.0 CRs of this document.)

2. Copy the CR package to the server on which the Deployment Manager is installed. Decompress the CR package downloaded in the step #1 into a temp directory.

3. If applying the CR to a clustered environment, ensure the WebSphere Application Server Deployment Manager is started and all node agents and application servers are shutdown.

4. Run the IBM Installation Manager from the server on which the Deployment Manager is installed to apply the CR.

5. Configure the repository in the IBM Installation Manager

  1. From the IBM Installation Manager menu, click File > Preferences.
  2. Click Repositories from the left navigation > Add Repository
  3. Enter the full path to the CR that you downloaded or click Browse to navigate to the location of the CR and then click OK. (The location is the temp directory in step #2)

    In IC 5.0 CR1 for example: C:\IBM\Connections\update\fixes\LC_version_Fixpack\repository.config

    In IC 5.0 CR3 for example: C:\IBM\Connections\update\fixes\LC_version_Fixpack\Updates\repository.config
    Add Repository dialog
  4. The IBM Installation Manager indicates if it can connect to the repository.
  5. Click OK to save the new repository.

6. Apply the CR

  1. Click Update in the Installation Manager.
  2. The package group panel appears. Select the IC5 package group (the default is IBM Connections) and click Next.
  3. Review and accept the license agreement by clicking I accept terms in the license agreements and then click Next.
  4. Ensure that all the applications are selected and click Next.
    Note: All of the installed applications are selected by default. If you add any of the non-selected applications, those applications will be installed. If you clear any of the selected applications, those applications will be uninstalled.
  5. Enter the administrative ID and password of the Deployment Manager and click Validate. Once the administrative ID is validate, click Next.
  6. Review the summary information and click Update.
  7. When the update is completed, click Finish button.
  8. Start node agents, then perform a full synchronization to push the update to all nodes. Check the SystemOut.log of each nodeagent to ensure synchronization completed successfully.

4. Update Connections Databases

The necessary database updates are listed in Section 4 - Software Requirements and Recommended Updates of this document.

To apply the database updates:

a. Download the database script package for the CR. Refer to
Technote 1681028 for CR1
Technote 1694319 for CR2
Technote 1902944 for CR3
No Database updates for CR4

b. Review the steps to run the database update scripts for your database type.

c. Run the commands for your database type.

5. Upgrade FileNet Components

After applying an IBM Connections 5.0 CR, you must upgrade each of the FileNet components. Please read the entire install instructions before beginning the installation. The installation is a multiple step process for each of the components and the requirements are listed in technote 1683147.The topic "Post-update tasks" under "Updating IBM Connections 5.0 with the latest Cumulative Refresh (CR)" in the online documentation has important information on deploying the latest FileNet FixPacks and Interim Fixes.

There are examples of the FileNet installation process in the following technotes:


Important - IC 5.0 CR2 only: Due to a defect in the installation code on the AIX platform, the FileNet Collaboration Services (FNCS) must be installed manually for IBM Content Navigator Version 2 (2.0.3.2-ICN-AIX-FP002a). See Technote 1698362 for details.

Here is an overview of the installation of the FileNet components

  1. Update FNCE using the connections install scripts
    1. This step can take 45 minutes or more to run the update command
    2. This step requires the end user to map the FileNetEngine back to the HTTP Server
  2. Update FNCS CE using the connections install script
  3. Update FNCS using the connections install script
    1. This step requires the end user to map Navigator application back to the HTTP Server
  4. (IC 5.0 CR2 only) Manually install 5.2.1.0-P8CPE-IF001 for FNCE
    1. This includes uninstall/reinstall the Filenet Engine
    2. The Waltz / Sonata jar files must be restore as part of installation of the interim fix

    6. Update miscellaneous items

    This step is only required if you have a Cognos-Metrics installation. The step will upgrade the Cognos server from the IBM Connections 5.0 level to the CR1 level. This only needs to be done once when going from IC 5.0 to CR1 or above. For additional details on upgrading the Cognos server refer to technote 1696033.

    1. Download the latest version of the Cognos Wizard which are listed in Section 4 - Software Requirements and Recommended Updates of this document.
    2. Copy the Wizard package and decompress the wizard package downloaded in the step #1 into a temp directory.
    3. From the IBM Installation Manager menu, click File > Preferences.
    4. Click Repositories from the left navigation > Add Repository
    5. Enter the full path to the fix that you downloaded or click Browse to navigate to the location of the Cognos wizard and then click OK. (The location is the temp directory in step #2) and then click OK.

      For example: C:\IBM\Connections\update\IBM_Cognos_Install_platform\CognosWizard\repository.config
    6. The IBM Installation Manager indicates if it can connect to the repository.
    7. Click OK to save the new repository.
    8. Click Update in the Installation Manager.
    9. Click Cognos and Confirm that the Installation Manager panel indicates that this is the upgrade for Cognos to the latest CR
    10. Click Update and when the update is completed, click Finish button.

    The IC 5.0 CR installation is complete; start the environment and you should be on the latest 5.0 CR.

    Document information

    More support for: IBM Connections
    Install

    Software version: 5.0

    Operating system(s): AIX, Linux, Windows

    Reference #: 1683118

    Modified date: 05 September 2017


    Translate this page: