Preparation for TWSz migration (zWS z Workload Scheduler )

Question & Answer


Question

What actions need to be taken before migrating TWS z/OS (COMPID 5697WSZ01 )

Cause

migration

Answer

Changes made April 4, 2023 are marked with a vertical bar "|" in the left margin.
| For general issues regarding migration please refer to technote 213015 :
| https://www.ibm.com/support/pages/node/213015| 


Here are some considerations before/during a migration:

| (1) What steps are involved in a zWS Upgrade?

| - Install zWS with SMP/E from download from SHOPZ 
| - Customize zWS parameters and Verify Installation
| - Migrate zWS Database (AD, CP, LTP etc)
- Migrating User Customization (PIF Programs, TWS EXITs etc.)
| - Switching zWS (Production Environment)
- Perform Fallback if any Problem

Installation is covered in chapters 4 and 5 of the Planning and Installation Guide.
Migration is covered in chapter 6. If there is any discrepancy between the manual technote 213015, the technote should be followed 

(2) Selecting Migration Procedure

Migrating z/OS First or TWSz First or “at the same time”

We recommend migrating TWSz first considering possible fallback issues
Avoid concurrent migration of both TWSz and z/OS

Migrating Controller (Engine) First or Tracker (Agent) First or “at the same time”

- Controller first is recommended (Note if DIALOG SERVER is used, it must be at the same release and maintenance level as the controller)

(3) TWSz Installation issues:

SMF/JES EXIT Installation
– Use Highest Release and Highest PTF Level

Modify System Parameter (Migration)
– Specify New Release Library
– Module Name (EQQINITx and Suffix in IEFSSN)
– EQQMINOx program name changed to be authorized in IKJTSO

Allocating Data Sets
– Use previous production size (not size from SEQQSAMP samples)

Modify TWS Start Procedure (Migration)
– Specify New Release Library
– Use latest samples as new DDs may be added and other changes may be made (LRECL, BLKSIZE etc)


Modify CP extend/replan/trial job JCL
– Specify New Release Library
– Critical changes are made across releases. Use samples created by EQQJOBS as template for JCL

Modify LTP extend/modify/trial/print JCL
– Specify New Release Library
– LTPRIN/LTPROUT DD LRECL/BLKSIZE changed since 8.5 release

(4) GUIs

| DWC TWS Server

|– DWC must be at the same release as the controller OR a higher release 

(5) Migrating User Customization

User Program (PIF)
– Re-Link

TWS EXIT
– Re-Link

Subroutine Program (EQQUSINx)
– Re-Link

TWS Macro (JCC/AJR)
– No change

Batch Loader/BCIT Job
– Same JCL (Specify New Library)

Mass Update Job
– Re-create JCL in New Environment

JCC (Job Completion Checker)
– Message table in EQQJCLIB can be used as same as before

Dataset trriggering table (EQQDSLST)
- EQQDSLST in EQQJCLIB can be used as same as before

AJR (Automatic job recovery) JCL
– Can be used as same as before
– Case code definition module can be used as same as before

Message Library
- ALWAYS use library from new release
– Re-customize if modified (example- if messages were made into WTOs)

TWS TSO ISPF Dialog Panel
- ALWAYS use library from new release
– Re-customize if modified

(6) Datastore ( data store )
- the datasets EQQPKIxx EQQSKIxx EQQUDFxx EQQSDFxx do not require any migration (they can be used unchanged from previous release). The datastore task JCL must
-use new level of SEQQLMD0 (either in STEPLIB or from LINK LIST ( LNKLST )


|  |(7) Switching zWS
- Practice with test environment
- Remember output files for EQQICTOP (EQQICNVS) job must be EMPTY before running the job
- Practice fallback also

Considerations
- Stop Automatic Job Submission
– When to extend CP or run REPLAN (always do AFTER migration)
– Will IPL be used to make system changes (exits, subsystems, authorized load modules) link list) or this be done dynamically?
- Validating New TWSz with Dummy Jobs
– Verify TWSz functions with test System
- Avoid use of new functions until confident that a fallback will not be needed

[{"Type":"MASTER","Line of Business":{"code":"LOB35","label":"Mainframe SW"},"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSWL3F","label":"IBM Z Workload Scheduler"},"ARM Category":[{"code":"a8m0z0000001fw9AAA","label":"ZOS-\u003EIZWS-\u003EMigration to a new release"}],"ARM Case Number":"TS000000000","Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"All Versions"}]