Maximo 7.5.0.3 Modifying Availability in Assignment Manager

Question & Answer


Question

Is there a way to modify labor availability in the Assignment Manager in Maximo 7.5.0.3 and above?

Answer

Suppose that you would like to add 2 hours to labor availability:

1. From the Assignment Manager main screen, click on the "Modify Availability" icon for the labor code.

2. From the "Modify Availability" dialog box, select the desired date and click on the "Modify" button:



3. Enter the following info and click OK:
Start Time = 3:00 PM
End Time = 5:00 PM
Reason Code = WORK



As result, notice that in the Assignment Manager main screen, the labor availability has been modified from 8:00 to 10:00.

[{"Product":{"code":"SSLKT6","label":"IBM Maximo Asset Management"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Component":"Assignment Manager","Platform":[{"code":"PF002","label":"AIX"},{"code":"PF010","label":"HP-UX"},{"code":"PF016","label":"Linux"},{"code":"PF027","label":"Solaris"},{"code":"PF033","label":"Windows"}],"Version":"7.5","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]