Problem(Abstract)

Process Control events that use activities with Parameter values of Date/Age of Docs or Age do not complete successfully in Unattend. When the Date/Age parm is blank, it works; but "blank" is an unrealistic choice. These are the affected parameters:

GDW_Audit_Rpt

GDW_Audit_Purge

GDW_Document_Rpt

GDW_Document_Purge

GDW_ExtData_Delete

Resolving the problem

Unattend.exe module correction needed. Apply at minimum Fix Pack 2. (5.3.1.2) from IBM Fix Central.

See also APAR IC91356: PROCESS CONTROL EVENTS FAILING WHEN DAYS / DATE USED

Document information

More support for: Sterling Gentran:Server for Microsoft Windows
Mapping and Translation

Software version: 5.3.1

Operating system(s): Windows

Reference #: 1633980