Calculation explained for -Earliest Next Due Date?(PM.ERLSTWOGENDATE)- field in Maximo Base Services?

Technote (FAQ)


Question

How is the field -Earliest Next Due Date (PM.ERLSTWOGENDATE)- calculated in Maximo Base Services?

Answer

PM.ERLSTWOGENDATE = Earliest next due date for a work order generated from this PM.
This is calculated from the PM tab in the PM application - 'Work Order Information' section

To set the Earliest next work order generation date, the code checks for:

Time Based (PM.nextdate and PM.extdate) and Meter Based Frequency

If it finds any of the above scenarios,namely PM.nextdate or PM.extdate or if its the 'Meter Based Frequency', then it gets the 'Estimated Meter Due Date'.

The calculation will find the earliest meter based due date taking in consideration all meters listed on the PM:

- ASSETMETER - lastreadingdate
- ASSETMETER - average

If no date can be generated for this PMMeter, null will be returned.

Note: Please keep in mind that if seasonal dates are involved, the calculation will be influenced accordingly.

Cross reference information
Segment Product Component Platform Version Edition
Systems and Asset Management IBM SmartCloud Control Desk Not Applicable AIX, HP-UX, Linux, Solaris, Windows 7.5, 7.5.1
Systems and Asset Management Tivoli Asset Management for IT Not Applicable AIX, HP-UX, Linux, Solaris, Windows 6.2.8, 7.1.1, 7.1.2, 7.5
Systems and Asset Management Tivoli Change and Configuration Management Database Not Applicable AIX, Linux, Windows, Solaris, HP-UX 6.2.8, 7.1.1, 7.1.2, 7.5
Systems and Asset Management Tivoli Service Request Manager Not Applicable AIX, Linux, Solaris, Windows 2003 server 6.2.8, 7.1, 7.1.2, 7.5

Rate this page:

(0 users)Average rating

Add comments

Document information


More support for:

IBM Maximo Asset Management
Assets

Software version:

6.2.8, 7.1.1, 7.1.2, 7.5

Operating system(s):

AIX, HP-UX, Linux, Solaris, Windows

Reference #:

1625145

Modified date:

2014-02-26

Translate my page

Machine Translation

Content navigation