Need to understand usage of fincntrl.ischargeable


Technote (FAQ)


Question

I am trying to find documentation on the usage of the Financial Cost Management application, specifically the “Is Chargeable” flag.

Answer

The Cost Management application represents the financial entities that will primarily be imported from an external system (e.g. Oracle Financials / Oracle Projects).

The Maximo Cost Management application stores work breakdown structures and summarised project and task costs at the Maximo site level.

The integration process assigns a unique financial control ID to each project and task it adds to Maximo. It also provides project tracking information to Maximo work orders and other transactions, to provide Oracle Projects with complete and accurate data.

The “Is Chargeable” (FINCNTRL.ISCHARGEABLE) field basically indicates whether costs can be collected for this cost entity or not. It is used in the Maximo Cost management application.

Please note, you add and modify projects and tasks in Oracle PA, not in Maximo.

When associating Projects and Tasks with Work Orders. The “Is Chargeable?” check box for the task must be selected, indicating that the task accepts charges.


Rate this page:

(0 users)Average rating

Copyright and trademark information

IBM, the IBM logo and ibm.com are trademarks of International Business Machines Corp., registered in many jurisdictions worldwide. Other product and service names might be trademarks of IBM or other companies. A current list of IBM trademarks is available on the Web at "Copyright and trademark information" at www.ibm.com/legal/copytrade.shtml.

Rate this page:


(0 users)Average rating

Add comments

Document information

IBM Maximo Asset Management

Cost Management


Software version:
6.2.1, 6.2.2, 6.2.3, 6.2.4, 6.2.5, 6.2.6, 6.2.7, 6.2.8, 7.1.1


Operating system(s):
Windows


Reference #:
1596793


Modified date:
2012-06-25

Translate my page

Content navigation