Question & Answer
Question
Why is there no event or action if a job runs past the deadline time set in an event rule?
Cause
This is by design.
Answer
The "Deadline" attributeFilter or property for a "JobLate" event cannot be used to insert a deadline for a job. The job deadline needs to be defined at the job level and the "Deadline" property for an event rule is a filter to add specificity to the event matching criteria.
[{"Product":{"code":"SSGSPN","label":"IBM Workload Scheduler"},"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Component":"Event Management (EDWA)","Platform":[{"code":"PF002","label":"AIX"},{"code":"PF010","label":"HP-UX"},{"code":"PF016","label":"Linux"},{"code":"PF027","label":"Solaris"},{"code":"PF033","label":"Windows"}],"Version":"8.6;9.1;9.2;9.3","Edition":"","Line of Business":{"code":"LOB45","label":"Automation"}}]