Question & Answer
Question
Is it possible to enter labor hours in the future?
Cause
When entering 'Labor Hours" that are in the future on a work order, you receive the above message.
Answer
There is a setting within Maximo 7X where this can be set to allow dates to be entered in the future.
Go to Administration> Organizations application.
Select the Organization you want this to be allowed in.
From the "Select Action" menu, select "Labor Options".
Update the "Future Labor Transaction Tolerance in Hours":
Click OK.
Now you can enter dates in the future within the work order on the Actuals tab.
Note: There are 24 hours in a day, multiply 24 by the amount of days ahead you want to allow users to be able to enter future dates.
Example:
To enter dates in the future up to 10 days you will set your "Future Labor Transaction Tolerance in Hours" to 240:00 hours.
[{"Product":{"code":"SSLKT6","label":"IBM Maximo Asset Management"},"Business Unit":{"code":"BU055","label":"Cognitive Applications"},"Component":"Work Order Tracking","Platform":[{"code":"PF027","label":"Solaris"},{"code":"PF033","label":"Windows"}],"Version":"7.1;7.1.1;7.1.2;7.5;7.6","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}},{"Product":{"code":"SSLKTY","label":"Maximo Asset Management for IT"},"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Component":null,"Platform":[{"code":"","label":"All"}],"Version":"","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}},{"Product":{"code":"SSWK4A","label":"Maximo Asset Management Essentials"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Component":null,"Platform":[{"code":"","label":"All"}],"Version":"","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]