RS00650: GUI IS TOO SLOW WHEN MOVING AN ACTIVITY EVEN WITH ACTIVITY EXTENT

Subscribe

You can track all active APARs for this component.

APAR status

  • Closed as fixed if next.

Error description

  • Load this instance.
    
    Select interaction scope "Activity" and insertion mode "Infinite
    capacity".
    Select first unfixed activity on resource "(25) Massojen
    valmistus" and
    move it from the 16th May to the following week for instance :
    it takes
    approx. 5s!!!
    .
    

Local fix

  • Changing the pegging strategy from "Dynamic Automatic" to
    "Dynamic FIFO" for all materials, the time spent in "Full
    repegging" is reduced to approx. 1.2s and time spent in "dynamic
    pegging" remais the same. So total time is now about 1.5s
    instead of 5s on my machine. This sounds a possible work-around
    while we are improving performance of case "Dunamic Automatic".
    

Problem summary

  • workaround provided to customer
    

Problem conclusion

Temporary fix

Comments

APAR Information

  • APAR number

    RS00650

  • Reported component name

    ILOG PPO

  • Reported component ID

    5724Y2600

  • Reported release

    330

  • Status

    CLOSED FIN

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2011-05-13

  • Closed date

    2011-08-15

  • Last modified date

    2011-08-15

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

Applicable component levels

  • R330 PSY

       UP



Rate this page:

(0 users)Average rating

Add comments

Document information


More support for:

IBM ILOG Plant PowerOps

Software version:

330

Reference #:

RS00650

Modified date:

2011-08-15

Translate my page

Machine Translation