PI50179: QMGR GOT ABEND 5C6 00E50076 AFTER RRS RESYNC PROCESS, THEN TERMINATED WITH REASON 00F30420

A fix is available

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • When we were testing RRS failure scenario, Queue Manager got
    ABEND 5C6-00E50076, then terminated with REASON=00F30420.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED: All users of WebSphere MQ Version 8          *
    *                 Release 0 Modification 0.                    *
    ****************************************************************
    * PROBLEM DESCRIPTION: An application putting or getting       *
    *                      messages in syncpoint while RRS is      *
    *                      restarted can cause the queue manager   *
    *                      to terminate with reason code 00F30420  *
    *                      and CSQV086E error message.             *
    *                                                              *
    *                      Other abends can be generated as result *
    *                      of this problem. For example,           *
    *                      5C6-00E50017 in CSQSTACK or             *
    *                      5C6-00E50076 in CSQVEUS1 or             *
    *                      5C6-0094000E in CSQMCCMT or             *
    *                      0C4-00000004 in CSQVSRX  or             *
    *                      0C4-00000011 in CSQSRSUP.               *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    An application has requested the queue manager to commit or
    backout a unit of work. While this is in progress, RRS is
    terminated and restarted. When RRS is restarted, a
    synchronization process is initiated to find and select units of
    work that were active when RRS was cancelled. Some of these
    units of work need to go to the deferred end of task (DEOT)
    process for termination and cleanup.
    
    RRS synchronization (CSQ3RRSR) can select and queue units of
    work for DEOT while they are still active in the queue manager.
    This results in units of work being terminated and cleaned up
    while still in use.
    

Problem conclusion

  • RRS synchronization (CSQ3RRSR) has been changed to check and
    wait for the units of work to be inactive before queuing them
    for deferred end of task processing.
    000Y
    CSQMCCMT
    CSQ3RRSR
    

Temporary fix

  • *********
    * HIPER *
    *********
    

Comments

APAR Information

  • APAR number

    PI50179

  • Reported component name

    WMQ Z/OS 8

  • Reported component ID

    5655W9700

  • Reported release

    000

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    YesHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2015-10-08

  • Closed date

    2015-11-04

  • Last modified date

    2016-01-04

  • APAR is sysrouted FROM one or more of the following:

    PI31280

  • APAR is sysrouted TO one or more of the following:

    UI32678

Modules/Macros

  • CSQMCCMT CSQ3RRSR
    

Fix information

  • Fixed component name

    WMQ Z/OS 8

  • Fixed component ID

    5655W9700

Applicable component levels

  • R000 PSY UI32678

       UP15/12/15 P F512 ¢

Fix is available

  • Select the PTF appropriate for your component level. You will be required to sign in. Distribution on physical media is not available in all countries.

[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSYHRD","label":"IBM MQ"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"8.0","Edition":"","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
04 January 2016