Error description

  • Description:
    Predecessor links are deleted on second plan import from MS
    Project if the parent summary task is changed even the user
    select the option 'Create only new Tasks' in step 3 of the
    import Wizard
    
    Steps to reproduce the issue:
    1. Create in MS Project three tasks Task A, Task A-1 and Task
    A-2.
    2. Make Task A a summary task and A-1 and A-2 child tasks.
    3. Add dates for the tasks and change to automatic control of
    dates.
    4. Export this as imp.xml from MS Project
    5. Create a new plan in RTC with preferably no existing content
    6. Import the imp.xml file into this plan. Accept all defaults,
    except to change the type of work items created to be tasks,
    rather than defects.
    7. This imports all the new tasks successfully.
    8. Go back to MS Project and alter the Task A to not be a
    summary task any more. Add a new Task B.
    9. Export this as imp.xml from MS Project.
    10. Import the new imp.xml file back into the same plan. Accept
    all defaults, except to change the type of work items created to
    be tasks, rather than defects. Make sure that in step 3 the
    option 'Create only new tasks' is selected.
    
    Actual result:
     The new Task B is imported, but the existing Task A has also
    changed to not be a parent type work item. The relation between
    the tasks has been removed on all three tasks.
    
    Expected result:
    Existing tasks are not updated
    
    For more information please see Work Item:
    https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.Wo
    rkItem/299345
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * all users/environments affected                              *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Predecessor links are deleted on second plan                 *
    * import from MS Project                                       *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • Fixed in code; verified and delivered in Rational Team Concert
    version 5.0
    

Temporary fix

Comments

APAR Information

  • APAR number

    PI10286

  • Reported component name

    RATL TEAM CONCE

  • Reported component ID

    5724V0400

  • Reported release

    403

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2014-01-24

  • Closed date

    2014-06-04

  • Last modified date

    2014-06-04

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    RATL TEAM CONCE

  • Fixed component ID

    5724V0400

Applicable component levels

  • R500 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSCP65","label":"Rational Team Concert"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"4.0.3","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
04 June 2014