Description: Predecessor links are deleted on second plan import from MS Project if the parent summary task is changed even the user select the option 'Create only new Tasks' in step 3 of the import Wizard Steps to reproduce the issue: 1. Create in MS Project three tasks Task A, Task A-1 and Task A-2. 2. Make Task A a summary task and A-1 and A-2 child tasks. 3. Add dates for the tasks and change to automatic control of dates. 4. Export this as imp.xml from MS Project 5. Create a new plan in RTC with preferably no existing content 6. Import the imp.xml file into this plan. Accept all defaults, except to change the type of work items created to be tasks, rather than defects. 7. This imports all the new tasks successfully. 8. Go back to MS Project and alter the Task A to not be a summary task any more. Add a new Task B. 9. Export this as imp.xml from MS Project. 10. Import the new imp.xml file back into the same plan. Accept all defaults, except to change the type of work items created to be tasks, rather than defects. Make sure that in step 3 the option 'Create only new tasks' is selected. Actual result: The new Task B is imported, but the existing Task A has also changed to not be a parent type work item. The relation between the tasks has been removed on all three tasks. Expected result: Existing tasks are not updated For more information please see Work Item: https://jazz.net/jazz/resource/itemName/com.ibm.team.workitem.Wo rkItem/299345
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * * all users/environments affected * **************************************************************** * PROBLEM DESCRIPTION: * * Predecessor links are deleted on second plan * * import from MS Project * **************************************************************** * RECOMMENDATION: * ****************************************************************
Problem conclusion
Fixed in code; verified and delivered in Rational Team Concert version 5.0
Temporary fix
Comments
APAR Information
APAR number
PI10286
Reported component name
RATL TEAM CONCE
Reported component ID
5724V0400
Reported release
403
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt
Submitted date
2014-01-24
Closed date
2014-06-04
Last modified date
2014-06-04
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
RATL TEAM CONCE
Fixed component ID
5724V0400
Applicable component levels
R500 PSY
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSCP65","label":"Rational Team Concert"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"4.0.3","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date:
04 June 2014