  • When a nested service in a client-side human service (CSHS)
    contains a postponed downstream of a coach, the coach might not
    display when launched after the postponement or might be
    displayed with no content. If you examine the (F12) browser
    console logs, you might see a SyntaxError.
    
    PRODUCTS AFFECTED
    IBM Business Process Manager (BPM) Advanced
    IBM BPM Standard
    IBM BPM Express
    

Local fix

  • Use a static value rather than a variable for the error code on
    the error end event.
    

Problem summary

  • When resuming a task, the client-side human service (CSHS) loads
    the variable values that were saved previously. If the root CSHS
    contains an error end event, the value given as the error code
    is treated like a variable name and the CSHS tries to load a
    value for it. As a result, the task fails because the error code
    might not have the appropriate syntax for a variable name.
    

Problem conclusion

  • A fix will be included in  IBM BPM V8.5.7 cumulative fix 2016.09
    that  correctly loads the saved data.
    
    To determine whether the cumulative fix is available and
    download it if it is, complete the following steps on Fix
    Central:
    
    1. On the Select product tab, select WebSphere as the product
    group, IBM Business Process Manager with your edition from the
    WebSphere options, All as the installed version, and All as the
    platform, and then click Continue.
    2. In the Text field, enter "cumulative fix?, and click
    Continue.
    

Temporary fix

Comments

APAR Information

  • APAR number

    JR56207

  • Reported component name

    BPM ADVANCED

  • Reported component ID

    5725C9400

  • Reported release

    857

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2016-06-27

  • Closed date

    2016-07-15

  • Last modified date

    2016-07-15

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    BPM ADVANCED

  • Fixed component ID

    5725C9400

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSFTN5","label":"IBM Business Process Manager Advanced"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"857","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
04 September 2023