A fix is available
APAR status
Closed as fixed if next.
Error description
Adding a Team in Process Designer takes several minutes. There is no indication from the screen that anything is happening until the team maintenance dialog appears several minutes after typing the new team name into the add team dialog. PRODUCTS AFFECTED: IBM Business Process Manager (BPM) Advanced IBM BPM Standard IBM BPM Express
Local fix
Problem summary
No additional information is available.
Problem conclusion
A fix will be incorporated into a later release that improves the performance of the system on opening a Team editor.
Temporary fix
Comments
APAR Information
APAR number
JR55211
Reported component name
BPM STANDARD
Reported component ID
5725C9500
Reported release
856
Status
CLOSED FIN
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2016-01-29
Closed date
2016-02-01
Last modified date
2016-02-01
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Applicable component levels
R856 PSN
UP
[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSFTDH","label":"IBM Business Process Manager Standard"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"856","Line of Business":{"code":"LOB45","label":"Automation"}}]
Document Information
Modified date:
16 October 2021