JR54352: COMPLETING A TASK IN A SUSPENDED BPD INSTANCE WITH A CALL TO THE BPM REST API INCORRECTLY ACTIVATES THE PROCESS

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as fixed if next.

Error description

  • A task of a BPD may be completed even if the process instance is
    in state 'suspended' to prevent that task workers who had
    started working on the task from loosing their work. However the
     process instance is supposed to remain in state 'suspended' and
     follow-on navigation only occurs once the process is resumed.
    

Local fix

  • N/A
    

Problem summary

  • To be fixed in next release. No formal fix is planned for the
    current release.
    

Problem conclusion

Temporary fix

Comments

APAR Information

  • APAR number

    JR54352

  • Reported component name

    BPM ADVANCED

  • Reported component ID

    5725C9400

  • Reported release

    856

  • Status

    CLOSED FIN

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2015-09-22

  • Closed date

    2015-12-09

  • Last modified date

    2015-12-09

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    BPM STANDARD

  • Fixed component ID

    5725C9500

Applicable component levels

  • R856 PSN

       UP