  • During performance analysis of the high degree of chattiness
    between the Process Designer and Process Center on BPM 7.5.1,
    we found that extra network trips are made.
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:  Users of BPM Express, BPM Standard and BPM  *
    *                  Advanced.                                   *
    ****************************************************************
    * PROBLEM DESCRIPTION: During performance analysis of the      *
    *                      high degree of chattiness               *
    *                      between the Process Designer and        *
    *                      Process Center on BPM 7.5.1,            *
    *                      we found that extra network trips are   *
    *                      made.                                   *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    During performance analysis of the high degree of chattiness
    between the Process Designer and Process Center on BPM 7.5.1,
    we found that extra network trips are made.
    Changes were done to remove 2 server trips per EJB call. For
    networks with high latency, this makes a big difference.
    

Problem conclusion

  • The extra network trips were removed and performance improved.
    
    The fix is available as a part of the JR42012 ifix package
    (http://www-01.ibm.com/support/docview.wss?uid=swg1JR42012)
    and needs to be installed as follows:
    - Install JR42012 on both Process Designer and Process
    Center/Server using IM
    - On Process Center/Server run bpmprofileUpgrade as outlined in
    http://www-01.ibm.com/support/docview.wss?uid=swg27022245#recove
    rFailure
    

Temporary fix

Comments

APAR Information

  • APAR number

    JR42113

  • Reported component name

    BPM ADVANCED

  • Reported component ID

    5725C9400

  • Reported release

    751

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2012-02-29

  • Closed date

    2012-04-18

  • Last modified date

    2012-04-18

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    BPM ADVANCED

  • Fixed component ID

    5725C9400

Applicable component levels

  • R750 PSY

       UP

[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSFTN5","label":"IBM Business Process Manager Advanced"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"7.5.1","Line of Business":{"code":"LOB45","label":"Automation"}}]

Document Information

Modified date:
12 October 2021