IV93260: ACTUAL START DATE IS GETTING CLEARED WHEN GANTT DEPENDENCIES ARE FIXED AND THE GANTT SAVED

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as fixed if next.

Error description

  • 1) Create a Capital Project after entering all the required
    field values.
    
    2) Click Schedule tab and add tasks to Project Tasks Gantt
    section or from Project Tasks section.
    
    3) Set dependency between all tasks.
    
    4) Open a task and set actual start date.  Save and close the
    record.
    
    5) Change either Plan Start/Plan End or Calculate Project From
    value so that Project task Gantt section shows either
    Constraints or dependency error.   If Calculated Project From
    is set to Start change the Plan Start date to a future date
    than the current Calculated start value.If Calculated Project
    From is set to End, prepone the Plan End date or set an earlier
    Plan End date than current Plan End date.
    
    6) Click Fix Constraints or dependency error icon and click
    Save icon in Gantt section. Open the task that has Actual Start
    date set in step #4.
    
    Issue: Actual Start date value is cleared.  If Gantt updates
    Planned Start date of a task while correcting invalid
    dependencies in Gantt section, then the Actual Start date value
    gets cleared.
    

Local fix

  • NO
    

Problem summary

  • Actual % is 100% set the Actual Start Date, Actual End Date,
    Actual Working Hours, Actual Duration to Planned values
    Actual % is anything else > 0 set the Actual Start Date to the
    Planned Start Date.
    Actual % is 0 and Actual Start Date has a value set Actual
    Start Date to Planned Start Date otherwise leave it alone.
    

Problem conclusion

  • Gantt Scheduler will honor business logic from Tasks to keep
    Actual Start and Planned Start Dates in sync unless the Actual
    Start date is cleared.
    This is targeted to the 1h2017 release.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IV93260

  • Reported component name

    TRI APPLCATION

  • Reported component ID

    5725F26AB

  • Reported release

    351

  • Status

    CLOSED FIN

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2017-02-09

  • Closed date

    2017-03-02

  • Last modified date

    2017-03-02

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • 999
    

Fix information

Applicable component levels

  • R352 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSHEB3","label":"IBM TRIRIGA Application Platform"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"351","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
30 March 2022