Direct links to fixes
APAR status
Closed as fixed if next.
Error description
We have noticed that after upgrading to 3.4.2, any TRIRIGA object that makes use of scheduling does not transition once the SCHEVENTSTART time comes to pass. Specifically the 'Mail' module\'Scheduled Events' Form\'Event Status' field, does not transition out of CREATED into STARTED or COMPLETED when the Start Datetime = CURRENT TIME. For example, PM Work Tasks never make it into Active state.
Local fix
No.
Problem summary
Resolved an issue where a decimal value was erroneously used in an ID field for Scheduled Events. This is targeted for the 2H2015 release and the 3.4.2.1 fix pack.
Problem conclusion
Temporary fix
As a temporary fix for SQL Server run the following script: update t_scheduledevents set trieventidnu = ROUND(trieventidnu, 0, 1) GO alter table t_scheduledevents alter column trieventidnu numeric(32,0) GO
Comments
APAR Information
APAR number
IV76293
Reported component name
TRI APPLCATION
Reported component ID
5725F26AB
Reported release
342
Status
CLOSED FIN
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt
Submitted date
2015-08-24
Closed date
2015-08-28
Last modified date
2015-08-28
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
999
Fix information
Applicable component levels
R342 PSY
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSHEB3","label":"IBM TRIRIGA Application Platform"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"342","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]