Error description

  • We have noticed that after upgrading to 3.4.2, any TRIRIGA
    object that makes use of scheduling does not transition once
    the SCHEVENTSTART time comes to pass.
    
    Specifically the 'Mail' module\'Scheduled Events' Form\'Event
    Status' field, does not transition out of CREATED into STARTED
    or COMPLETED when the Start Datetime = CURRENT TIME.
    
    For example, PM Work Tasks never make it into Active state.
    

Local fix

  • No.
    

Problem summary

  • Resolved an issue where a decimal value was erroneously used in
    an ID field for Scheduled Events.
    This is targeted for the 2H2015 release and the 3.4.2.1 fix
    pack.
    

Problem conclusion

Temporary fix

  • As a temporary fix for SQL Server run the following script:
    update t_scheduledevents set trieventidnu = ROUND(trieventidnu,
    0, 1)
    GO
    alter table t_scheduledevents alter column trieventidnu
    numeric(32,0)
    GO
    

Comments

APAR Information

  • APAR number

    IV76293

  • Reported component name

    TRI APPLCATION

  • Reported component ID

    5725F26AB

  • Reported release

    342

  • Status

    CLOSED FIN

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt

  • Submitted date

    2015-08-24

  • Closed date

    2015-08-28

  • Last modified date

    2015-08-28

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • 999
    

Fix information

Applicable component levels

  • R342 PSY

       UP

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSHEB3","label":"IBM TRIRIGA Application Platform"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"342","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]